job no. job description client commencement date completed date/percentage
21 Sub-Contract for Pilecap Works -SDE
AKM Sdn Bhd 10.06.2006 100%
22 Sub-Contract for Earthwork -SDE Ranhill Engineers & Constructors Sdn. Bhd 27.09.2007 100%
23 Sub-Contract for Bukit Damansara Kuala Lumpur
Tan Sri Hamdan 05.10.2007 100%
24 Sub-Contract for Execution & Completion of Hoarding & Signboard at Jalan Raja Chulan
Public Mutual Berhad 17.01.2008 100%
25 Sub-Contract for Horse Stable Tan Sri Hamdan May 08 100%
26 Sub-Contract for Government Apartments at Putrajaya
UEM Builders Berhad 28.02.2008 100%
27 Sub-Contract for TNB Sub Station Sub Structure Works, Perling Transmission Grid Resources Sdn. Bhd. 27.05.2008 100%
28 Sub-Contract for Australia Embassy, KL WTW Bovis Sdn. Bhd. 01.08.2008 100%
29 Sub-Contract for Underpass 1 Alloy Consolidated Sdn Bhd 05.02.2008 100%
30 Sub-Contract for WTW Bovis Malaysian Nature Society Oct 08 100%